Harmonic measurement, simulation, and filter design to IEEE 519 compliance.
VFDs, rectifiers, and arc furnaces inject harmonics. Capacitor banks resonate. Transformers heat. Motors over-vibrate. Utility imposes penalties. We measure, simulate, design tuned or detuned filters, and bring you back inside IEEE 519 · with the smallest filter that does the job.
Variable frequency drives now run 40-60% of industrial motors. Each is a non-linear load injecting 5th, 7th, 11th, 13th harmonics back into the bus. Capacitor banks installed for power factor correction become resonant tuned circuits at exactly the harmonic frequency that's being injected. The capacitors fail every 18 months. Transformers run hot. Motor bearings vibrate. Utility imposes harmonic distortion penalties. The single biggest hidden capex driver in brownfield plants we audit is harmonic distortion that nobody measured because nobody was looking. A harmonic study quantifies it, designs the filter, sizes the capex, and gives you a clear ROI case.
CEng MIE India-signed deliverables · LiDAR-powered where applicable · digital twin handover ready · routes to the Power System Studies practice lead within 24 hours.
On-site measurement at PCC + major LV buses using IEC 61000-4-7 / IEEE 519-compliant power quality analysers. Minimum 7-day window across operating cycles.
ETAP or DigSILENT Harmonic Analysis module configured. Non-linear load sources (VFDs, rectifiers, arc furnaces) modelled per manufacturer harmonic spectrum or measured signature.
Frequency scan from 0-5000 Hz. Resonance peaks identified. Existing capacitor banks tested for resonance risk.
Tuned filters (5th, 7th, 11th, 13th) or detuned reactors sized for IEEE 519 compliance at PCC. Active harmonic filter sized where passive solution is impractical (e.g. variable load mix).
Filter design validated by re-simulation. Expected post-filter TDD and THD tabulated per bus. CEng MIE-signed report. Filter SOR (Statement of Requirements) ready for procurement.
Reports reference the international and national standards your regulators, F500 audit teams, and corporate process safety leads cite. Every deliverable signed by a Chartered Engineer (CEng MIE India).
Three landmark engagements from our verified roster · quantified outcomes, no client names disclosed without written permission.
Capacitor bank failing every 14 months root-caused to 5th harmonic resonance from new VFD installation. Designed detuned reactor solution. Bank lifespan restored to 8+ years.
TDD measured at 11.2% (IEEE 519 limit: 5%). Designed active harmonic filter. Post-install TDD 3.4%. PCC violation resolved.
Combined arc furnace + VFD load created multi-harmonic resonance condition. Hybrid passive + active solution designed. Utility penalty avoidance seven-figure/yr.
Tell us your plant, region, and scope · a named Chartered Engineer responds within 24 hours.